new STD clinic building

 


Milestones

2003.03.10 Constructions started
 
  • KD Ebem & Company
 
  • Cost: Rs. 40,500,395.35
   
2007.12.24 Constructions Stopped
   
2010.09.29 Constructions Restarted
 
  • Lion Asian Constructions
 
  • Cost: Rs. 39,500,000.00
   
2011.12.26 Constructions Stopped
   
2012.08.26 Constructions Restarted
 
  • PSM Construction
 
  • Cost: Rs. 2,745,360.00
 
  • Given Constructions Completed
   
2013.03.09 Constructions Restarted
 
  • Jayasundara Construction
 
  • Cost: Rs. 3,124,962.40
 
  • Given Constructions Completed
   
2013.03.09 Constructions Restarted
 
  • Susil Builders
 
  • Cost: Rs. 1,834,750.00
 
  • Given Constructions Completed

2013 May

  • Gynaecological clinic and pharmacies have commenced